How to install drip edge flashing to a new roof.
Roofing gutter drip edge installation.
Use a flat pry bar and hammer to pry the nails out of the drip edge gently.
Place a nail at one end then the other.
Slip the wide flat flange of the material all the way under the first course of roof shingles as illustrated.
Ideally it is recommended to nail about every 12 inches.
Some rain runoff by capillary action runs up under the shingle drip edge and down the fascia behind the gutter installing drip edge on a new roof or re roofing job.
This is important to protect damage to your fascia soffits rafters.
It is best to install a drip edge on a day with warm weather because it makes it easier for the shingles to be stripped back.
If it doesn t pull the drip edge out slightly from under the shingles.
Make sure the corner is tight and that the bottom edge is tight to the fascia before nailing off the drip edge.
Installing drip edge on your roof.
However keep in mind that tile shingles or materials like slate cannot be lifted so always install a gutter apron for new roofing.
Once free slide the drip edge out and discard.
With without rain gutters.
To install a drip edge on a newly constructed roof or on a re roofing job attach the drip edge along the roof s eaves first.
You may need to nail through the starter strip into the drip edge.
While the vertical leg should be placed 1 4 1 2 away from the fascia.
Begin at the lower corner of the roof and gradually progress to the top.
Apply a continuous bead of cement along the top of the drip edge then press down on the shingle.
You can use nails to tightly secure it.
Make sure the outer edge extends over the gutter.
There was no way that the gutter installe was going to get the upper edge of the gutter behind the drip edge.
For drip edge installation align it for directing water flow into gutter alongside the roof edges.
How to install a drip edge.
It can be done.
Ask this old house general contractor tom silva demonstrates the importance of a properly installed drip edge subscribe to this old house.
The roof leg should extend a minimum of 2 back onto the roof sheathing.
The roofer installed the drip edge tight against the fascia.
Be sure to tuck the drip edge under the starter strip and felt paper.
Gently lift up the shingles on the edge of the roof and locate the nails holding the existing drip edge onto.
Slide the corner tight to the fascia.
Tools supplies tin sn.